A critical chain schedule: Design, Build A, Build B and Test across the design, build and test engineers, ending in a partly used project buffer before the promised date

Critical Chain Project Management (CCPM) Explained

CCPM

Critical Chain Project Management (CCPM) is a method for planning and running projects that schedules around both task dependencies and resource availability, removes padding from individual task estimates, and protects the delivery date with shared buffers. Buffer status then tells everyone which work matters most today.

Picture Monday morning in a busy engineering department. Twelve projects are open. The one test rig has been promised to four of them this week. Every estimate on the plan carries a few quiet days of safety, and the project that will really miss its date is not the one everybody is talking about.

Nobody in that room is lazy. Projects are rarely late because people work too little. More often they are late because too many projects compete for the same skills, every estimate hides its own safety time, and nobody can see which delay actually threatens the delivery date.

The problem isn’t always how much capacity you have. It’s how that capacity is shared across competing projects.

Sometimes a team really is short of a skill, and no planning method fixes that. Often, though, the people are there and the trouble is the order in which work reaches them. Critical Chain Project Management (CCPM) was designed for that situation, and it also makes a genuine shortage visible. In this guide you’ll see what CCPM is, where it came from and how its buffers work. Just as important, you’ll see when it is not the right tool. All the worked examples use small, illustrative numbers so you can follow the logic; real projects are messier.

CCPM in 60 seconds

  • Plan around peopleThe critical chain is the longest chain of work once you account for who has to do it.
  • Pool the safety timePadding moves out of tasks into shared buffers that protect the date.
  • Let buffers set prioritiesRed, orange or green tells everyone which work matters most today.
  • Start fewer at onceRelease new projects when the most heavily loaded skills have capacity.

What is CCPM?

Critical Chain Project Management (CCPM) is a method for planning and running projects that schedules around both task dependencies and resource availability, removes padding from individual task estimates, and protects the delivery date with shared buffers.

The method is also called the critical chain method or critical chain scheduling. CCPM is based on the Theory of Constraints (TOC). Instead of trying to make every task finish on time, it focuses on the one sequence of work that determines when the project can finish: the critical chain.

That is the big shift. In a traditional plan every task has a date, and every missed date is a small crisis. CCPM stops chasing those dates. It asks a different question: is the buffer that protects the delivery date being used up faster than the work is getting done? (Leach, 1999)

A critical chain schedule at a glanceHover or tap a number
A critical chain schedule with feeding and project buffers Three resources over 18 days. The critical chain runs Design (design engineer), Build A and Build B (build engineer), Test (test engineer), then a project buffer. A side chain, Manual (design engineer), ends in a feeding buffer before Test. The orange part of the project buffer shows how much has been consumed. DesignengineerBuildengineerTestengineer Day 048121418 Design · 4d Test · 2d Build A · 5d Build B · 3dboth need the build skill Manual · 4d Feeding Project buffer Promised date: day 18 1 2 3 4 5
  1. Critical chain (purple): the longest chain of work once you include who does it. It sets how long the project takes; the project buffer after it sets the promised date.
  2. Resource dependency: Build A and Build B don’t depend on each other, but both need the build engineer, so they run one after the other.
  3. Feeding buffer: the side task Manual finishes early on purpose, so a delay there doesn’t hold up Test.
  4. Project buffer: the safety time taken out of the tasks, pooled at the end. Orange shows how much is used.
  5. Promised date: day 18, protected by the buffer instead of by padding every task.
Illustrative example.

Where CCPM comes from

Unusually for a management method, CCPM reached most people through a novel. Dr. Eliyahu M. Goldratt, author of The Goal and founder of the Theory of Constraints, first presented the critical chain idea at the International Jonah Conference in 1990 (Ghaffari & Emsley, 2015). In 1997 he published the business novel Critical Chain, which applied TOC to project management and gave the method its name (Goldratt, 1997).

  1. 1984The Goal introduces the Theory of Constraints to a wide audience.
  2. 1990Goldratt first presents the critical chain idea at the International Jonah Conference.
  3. 1997Critical Chain applies TOC to projects and names the method.
  4. 1998–99Newbold’s Project Management in the Fast Lane and Leach’s article in the Project Management Journal turn the idea into practice.
  5. TodayUsed in R&D, engineering, construction, maintenance and other work where many projects share scarce people.

Since then, practitioners and researchers have tested the idea, argued about it and refined it. A review of the research by Ghaffari and Emsley (2015) covers the main lines of work: buffer sizing, multi-project scheduling and behaviour.

Critical chain vs critical path

The critical path is the longest chain of task dependencies, and it assumes people and equipment are available when the plan says they are. The critical chain also accounts for resource dependencies, where the same team, skill or machine is needed in several places at once. CCPM then removes padding from individual tasks and protects the end date with buffers.

The quickest way to understand CCPM is to compare it with the method most planners already know. The critical path is “the sequence of activities that represents the longest path through a project, which determines the shortest possible duration” (PMI, 2017). The classic critical path calculation considers task dependencies only (Kendall, 2020): it assumes the people and equipment are available when the plan says they are. Planners can level resources afterwards, but then the critical path no longer tells you which work really drives the end date.

The critical chain is the longest chain of dependent work when you consider both task dependencies and resource dependencies. A resource dependency exists when the same person, team or machine is needed in several places at the same time.

Try it: click to compare two schedules
Critical path versus critical chain Design by the design engineer takes 4 days. Build A (5 days) and Build B (3 days) both need the build engineer and both follow Design. Test by the test engineer takes 2 days and needs both builds. Ignoring resources, Build A and B run in parallel and the project takes 11 days. Because the build engineer cannot do both at once, Build B has to wait, and the realistic finish is day 14. DesignengineerBuildengineerBuildengineerTestengineer Design · 4d Build A · 5d Build B · 3d Test · 2d Finish: day 11 Build skill double-booked
Finish dateDay 11
What it assumesThe build engineer can do two builds at once
Illustrative example.

With the same task estimates, the critical chain can never be shorter than the critical path, and in a resource-constrained environment it is often longer. That makes it the more honest answer to “when can we really finish?” A CCPM plan can still promise an earlier date than a padded critical path plan, because it uses focused estimates and one shared buffer instead of safety in every task. Whether it does depends on how much padding the original plan carried.

Critical path (CPM) and critical chain (CCPM) compared.
AspectCritical path (CPM)Critical chain (CCPM)
Schedules aroundTask dependenciesTask dependencies and who does the work
Safety timeUsually hidden inside each task estimateRemoved from tasks, pooled in shared buffers
Progress is tracked byTask dates, percentage done or earned valueBuffer consumed vs chain completed
Daily priorities come fromTask deadlines and float (slack)Buffer status, the same rule in every project
Many projectsEach one scheduled on its ownProjects released when shared people have capacity

For a detailed side-by-side comparison, read CCPM vs. Critical Path (CPM): Differences and When to Use Each.

The five building blocks of CCPM

The comparison shows what CCPM changes. The five building blocks below show how: two shape the plan, two protect and steer it, and one changes how people work day to day.

1. A resource-feasible schedule

A plan that books the build engineer for two builds on the same day isn’t a plan. It’s a wish.

A schedule is resource-feasible when no person, team, skill or machine is planned for more work than it can do on any day. Getting there is called resource levelling: when two tasks need the same resource at the same time, one of them moves. CCPM levels the plan first, and when tasks compete for a resource, work on the longest chain gets it first. Only then does it identify the critical chain (Goldratt, 1997; Leach, 1999).

Here is the plan from the critical chain example above, seen from the build skill’s side:

Try it: the build skill’s week, before and after levelling
Resource levelling: the build skill's tasks and workload before and after levelling On paper, Build A (days 4 to 9) and Build B (days 4 to 7) both start on day 4, so the build skill is planned at 200% for three days. After levelling, Build B starts on day 9 when Build A is finished, the build skill is never above 100%, and the project finish moves from day 11 to day 14. Build ABuild BBuild skill load per day Day 02468101214 Build · 5 days Build · 3 days 100%capacity ← double-booked: 200%
Build skill at most200%
Project finishDay 11
Can the team do it?No
Same tasks and estimates as the critical chain example above. Illustrative example.

The result is a schedule people can actually carry out. It is often later than the plan on paper, but it is honest, and it shows which skill really drives the end date. It also separates two problems that look the same from a distance: work that is badly sequenced, which levelling fixes, and a skill that is short for months on end, which only hiring, outsourcing or saying no to work will fix.

2. Focused task estimates

Ask anyone for an estimate and you get a safe one. That is perfectly sensible: nobody wants to be the person who made the project late. But add up twenty safe estimates and the plan is mostly safety time, and as you’ll see below, most of it gets used up whether it is needed or not. CCPM removes that individual padding and plans with focused durations: aggressive but achievable, often described as an estimate with about a 50% chance of being met (Leach, 1999; Altarazi & Bao, 2015). The safety time doesn’t disappear. It is moved to where it protects the project as a whole.

Try it: where the safety time goes
Padded task estimates versus focused estimates with a project buffer Four tasks padded to 10, 8, 6 and 6 days give a 30-day plan. With focused estimates of 5, 4, 3 and 3 days plus a project buffer of half the removed safety, 7.5 days, the plan is 22.5 days. 0102030 days
Promised dateDay 30
Where the safety sitsHidden inside every task
Illustrative numbers, not a formula to apply as is. Hatched = safety time. Cutting estimates in half and using a buffer of half the removed safety is the classic “cut and paste” rule of thumb from early CCPM practice; other sizing methods exist (see building block 3).

3. Buffers instead of padding: the CCPM buffer types

Classic CCPM uses three buffers: the project buffer, feeding buffers and resource buffers (Goldratt, 1997; Leach, 1999). Many tools add a fourth, the milestone buffer.

Project buffer. The safety removed from tasks on the critical chain is aggregated into one buffer at the end of the chain. It absorbs variation and protects the delivery date. The classic rule of thumb sizes it at 50% of the safety removed from the critical chain. Newbold (1998) proposed a statistical alternative, the square root of the sum of the squared safety times, which gives smaller buffers for long chains. For long chains the 50% rule can produce a larger buffer than needed (Herroelen & Leus, 2001).

Feeding buffers. Where a non-critical chain feeds into the critical chain, a feeding buffer protects the critical chain from delays on that side branch (Hu et al., 2016).

Milestone buffers. Not part of Goldratt’s original description, but common in practice. Where a project has contractual or intermediate deadlines, a buffer can protect the chain leading to that milestone. (LYNX supports project, feeding and milestone buffers.)

Resource buffers. These are not time blocks but signals: alerts that make sure a critical resource is ready when critical-chain work arrives (Hu et al., 2016).

Four buffer types on one scheduleHover or tap a number
Project, feeding, milestone and resource buffers in a CCPM schedule The critical chain runs Spec, Design, a milestone buffer before a customer milestone, Build and Test, then a project buffer before the promised date. A side chain, Docs, ends in a feeding buffer where it joins Test. A resource buffer alerts the tester before Test starts. Customer milestone Spec Design Build Test Project buffer Promised date Docs (side chain) Feeding Tester alerted early 1 2 3 4
  1. Project buffer protects the promised date. Orange shows how much is used.
  2. Feeding buffer stops a late side chain from delaying the critical chain.
  3. Milestone buffer protects an intermediate or contractual date.
  4. Resource buffer is an alert, not time: the tester knows the work is coming.
Illustrative example. LYNX supports project, feeding and milestone buffers.
In LYNXThe project window
LYNX project Gantt: critical chain tasks outlined in red, a feeding chain in blue ending in a feeding buffer, a milestone, and the project buffer at the end with the share used per buffer

LYNX finds the critical chain for you. In the Gantt, critical-chain tasks are outlined in red and the feeding chain in blue. The feeding buffer sits where the side chain joins, and the project buffer at the end. On each buffer row, the Buffers column shows how much of that buffer is used: here 25% of the feeding buffer and 13% of the project buffer.

4. Buffer management and fever charts

Once work starts, CCPM boils status reporting down to one question: how much buffer have we used, compared with how much of the chain is complete? Using 30% of the buffer with half the chain finished is fine. Using 30% on day two is not. A fever chart shows exactly that, with red, orange and green zones.

Try it: read a fever chart
Fever chart Horizontal axis: share of the critical chain completed. Vertical axis: share of the project buffer consumed. The bottom zone is green, the middle orange, the top red. The plotted project moves as you change the sliders. 0%50%100% 0%50%100%Critical chain completed Buffer consumed
Green: on trackKeep going. No action needed.
Red: act nowOrange: plan a recoveryGreen: on track
The trend matters as much as the point: a line that climbs steeply means buffer is being used faster than the chain is completed. Zone lines are set per organisation; these follow the default slope in LYNX.

Thresholds turn that signal into action. In a simple setup, 35% buffer usage might trigger a warning and 65% an urgent status. Most tools draw sloped zone lines instead, so that the same buffer use is judged against how much of the chain is already done. Because buffer status changes with actual progress, priorities update as soon as people report progress, and everyone knows which tasks matter most today.

5. Less multitasking, more flow

Anyone who has juggled three projects knows the feeling: busy all week, nothing finished by Friday. CCPM and TOC treat that kind of multitasking, and too much work in progress (WIP), as one of the biggest hidden causes of delay. Fewer parallel tasks usually mean each piece of work finishes sooner and reaches the next person sooner, with fewer things dropped along the way. That is the relationship Little’s Law describes.

Try it: one tester, three releases. Click to compare
Multitasking versus focused work for one test engineer and three product releases The only test engineer has 10 days of testing for each of three product releases. Switching every 2 days and losing half a day each time a release is picked a release up again, release A is tested on day 32, B on day 34.5 and C on day 37. Testing one release at a time, A is done on day 10, B on day 20 and C on day 30. Release ARelease BRelease C Day 0102030 time lost getting back into a release (½ day per switch)
A testedDay 32
B testedDay 34.5
C testedDay 37
AverageDay 34.5
Illustrative example. Half a day per switch is a cautious assumption: Weinberg (1992) estimated that someone working on three projects at once loses about 40% of their time to switching, and lab studies show that every switch between tasks costs time (Rubinstein, Meyer & Evans, 2001).

CCPM teams often describe the working rule as the relay-runner ethic (Newbold, 1998, calls it the roadrunner mentality): when a task on the chain is ready, start it, work on it without switching, and hand it over as soon as it is done, rather than holding it until a planned date.

In LYNXMy activities
LYNX My activities in LYNX-X: started and ready-to-start tasks sorted by priority, each row marked red, orange or green by the most critical buffer it feeds, with task details on the right

Each person sees one list, sorted by priority. The row colour is the most critical buffer the task feeds, so the next task to pick up is always the top one, across all projects.

Multitasking is not the only thing that eats time. Remember the safety time that focused estimates took out of each task? Without CCPM, it usually disappears before anyone needs it, because of three well-known habits. They are the reason CCPM moves safety into shared buffers and asks for the relay-runner way of working above.

Where task safety time disappears
Student syndrome, Parkinson's law and the CCPM relay-runner approach Each task has an estimate of 10 days that includes 5 days of safety. With student syndrome, work starts on day 5 and any problem makes the task late. With Parkinson's law, the work spreads over all 10 days and the task never finishes early. With CCPM, work starts at once, takes 5 focused days and is handed over on day 5. Student SyndromeParkinson’s LawCCPM relay runner Starts late Work stretches to fill the time Focused · 5 days handed over on day 5 Day 0510 (estimate) late if anythinggoes wrong never early
Dashed outline = the padded 10-day estimate. In the first two rows the safety time is used up whether it was needed or not. Illustrative example.
  • Student Syndrome: starting work only when the deadline gets close. Goldratt (1997) named it. The safety time is spent waiting, so any problem makes the task late. CCPM answer: no padded deadline per task to wait for; start when the work is ready, as the relay runner does. Read more on why task estimates slip
  • Parkinson’s Law: “work expands so as to fill the time available for its completion” (Parkinson, 1955). A task estimated at 10 days rarely finishes in 7, so time saved early is never passed on. CCPM answer: focused estimates and handing work over as soon as it is done, so an early finish helps the next person on the chain.
  • Murphy’s Law: if something can go wrong, it will. Buffers plan for it. CCPM answer: the safety time sits in the project and feeding buffers, where it protects the whole chain, and the fever chart shows when it is running out. See Tackling Murphy’s Law with CCPM.

Put together, the five building blocks work as one system: a realistic schedule, short estimates, shared buffers, a single priority signal from the fever chart, and people who finish one task at a time. Leave one out and the others lose much of their effect. The next section shows how to put them in place.

How to implement CCPM, step by step

To implement CCPM, build the network, assign resources and skills, use focused estimates, level resources to find the critical chain, insert buffers, release new work only when the most heavily loaded skills have capacity, then manage priorities from buffer status. Building the schedule is the easier part. The rollout is what makes focused estimates and the priority rule stick.

Implementing CCPM has two parts: building and running a critical chain schedule, and getting an organisation to work with it. The seven steps below cover the first part. They follow the method as Goldratt (1997) described it and as Newbold (1998) and Leach (1999) worked it out for practice. The example in each step uses the same small, illustrative project as the diagrams above: a design engineer designs and writes the manual, a build engineer builds, a test engineer tests.

How to implement CCPM in 7 steps with a worked example: build the network, assign resources, use focused estimates, find the critical chain, insert a 7.5-day project buffer, release by capacity, manage the buffers by red, orange and green
The seven steps of critical chain project management with a worked example. Sources: Goldratt (1997), Newbold (1998), Leach (1999). Details and common pitfalls below.
  1. Build the network. Define the tasks and dependencies needed to reach the project goal. Watch out: work back from the goal, and keep tasks big enough to be meaningful but small enough to finish in days or weeks, not months.
  2. Assign resources and skills. Who or what does each task need? Watch out: plan by skill or role where you can, so the schedule shows which skills are the real constraint, not just which tasks overlap.
  3. Use focused estimates. Remove individual safety time from task durations. Watch out: a focused estimate is not a deadline. Many tasks will take longer, and that is what the buffer is for, so never blame people for missing one.
  4. Level resources and find the critical chain. Resolve resource conflicts; the longest remaining chain is the critical chain. Watch out: in a real plan the chain can jump between people and branches. Use software for anything beyond a few dozen tasks.
  5. Insert buffers. Add a project buffer at the end, feeding buffers where side chains join, and milestone buffers where needed. Watch out: half the removed safety is a common starting rule, not a law. Researchers have proposed many sizing methods (Herroelen & Leus, 2001), so review buffer use after the first projects.
  6. Release work deliberately. In a portfolio, start new projects only when the most heavily loaded skills have capacity (limit WIP). Watch out: this is the step organisations skip most, because it means saying “not yet” to a project. See CCPM across many projects.
  7. Execute and manage the buffers. Task owners report remaining duration; buffer status sets the priorities; management intervenes only where buffers turn red. Watch out: look at the trend on the fever chart, not one data point, and act on orange by planning a recovery before it turns red.
In LYNXUpdating a task
LYNX task details panel: the Ettc field (expected time to complete) of a started task, 4 days, with the prompt to enter the expected time to complete

Task owners don’t report a percentage done. They enter the expected time to complete in days (ETTC), and LYNX recalculates buffers and priorities from that.

Rolling CCPM out in your organisation

The schedule is the easy part. CCPM changes how people estimate, report and pick their next task, so the rollout matters as much as the method. In practice it usually looks like this:

  1. Start with one pilot. Pick one team or a small set of projects that share people, and prove it there first.
  2. Explain the why to everyone. Focused estimates only work when people trust that missing one will not be held against them.
  3. Agree the release rule with management. Decide who may start a new project and when, before the first plan is built.
  4. Replace task deadlines with one priority rule. Work on the task whose buffer is in the worst state, and report remaining days, not a percentage done.
  5. Hold a short, regular buffer review. Look only at orange and red projects and agree on actions.
  6. Measure and widen. Track on-time delivery and projects finished per quarter, then add teams and projects step by step.

Start simple. Teams that try to switch on every feature on day one tend to get lost; a first stage with one priority rule and a fever chart is enough to see whether CCPM works for you.

CCPM across many projects

Multi-project CCPM gives each project its own critical chain and buffers, then adds three things. New projects are released only when the most heavily loaded skill has capacity. One priority rule applies everywhere: the task whose buffer is in worse shape goes first. And a portfolio fever chart shows which few projects need help.

  • Release by capacity (staggering). New projects start when the most heavily loaded skill can take them, not when someone signs them off. In TOC this is the drum (or strategic) resource: its schedule is the drum beat that paces the whole portfolio, and the gap kept in front of it is called the capacity buffer.
  • One priority rule for every project. When two projects need the same person, the task whose buffer is in worse shape goes first.
  • A portfolio fever chart. Every project on one chart, so management can see which few need help and leave the rest alone.
Try it: four projects share one test team
Starting all projects at once versus releasing them by test team capacity Four projects each need 4 days of engineering by their own engineers and 3 days with one shared test team. Started together, all four reach testing on day 4, the test team rotates between them, and all four finish on day 16. Released every 3 days, each project reaches testing just as the test team is free, and they finish on days 7, 10, 13 and 16: the first 9 days sooner, the average on day 11.5 instead of 16, and the last no later. Project 1Project 2Project 3Project 4 Day 047101316 Engineering (own team)Testing (shared test team)Waiting for the test team
First project doneDay 16
Average finishDay 16
Last project doneDay 16
Same four projects, same people, same amount of work. Illustrative example; time lost to switching is not even counted.
In LYNXReleasing a new project
LYNX Release project dialog: a new project staggered behind released projects on the drum skill, with proposed start and due date and a Release button

The Release Wizard proposes a start date that is staggered on the drum skill, here the System Tester, so the new project slots in behind the work already released. You decide whether to release it.

Starting fewer projects at once often finishes more of them. In simulations, Cohen, Mandelbaum and Shtub (2004) found that controlling the number of projects in progress mattered at least as much as buffer management itself.

So much for how the method works. What can an organisation realistically expect from it, and where does it struggle?

CCPM benefits and limitations

CCPM aims for more reliable delivery dates, clear priorities, earlier signals and, in many cases, shorter lead times, by protecting the commitment with shared buffers instead of padding every task. It doesn't make work smaller or people faster. It needs leadership support, focused estimates that nobody is blamed for missing, and up-to-date remaining durations.

What CCPM aims to deliver

  • More reliable delivery dates. Buffers protect the commitment, not each task estimate.
  • Shorter lead times, in many cases. Less multitasking and less hidden padding. How much shorter depends on how much of both there was to start with.
  • Clear priorities. One shared signal, buffer status, tells everyone what to work on next.
  • Earlier signals. Buffer burn shows trouble long before a deadline is missed.
  • Better use of scarce resources across many projects.

What to be aware of

  • It’s a mindset change. Focused estimates only work if people aren’t blamed for overrunning an individual task. As Leach (1999) notes, CCPM can be “a catalyst for change”, which means leadership must support it.
  • Data discipline matters. Buffer signals are only as good as the remaining-duration updates behind them.
  • Multi-project CCPM is hard by hand. Levelling resources and recalculating buffers across a portfolio quickly needs software.
  • No guarantee. CCPM doesn’t make work smaller or people faster. Results depend on the starting point and on how consistently the rules are applied.

Herroelen and Leus (2001) found the core ideas sound but warned against applying rules of thumb blindly, in particular the 50% buffer rule and treating the first critical chain as fixed while work progresses.

Cohen, Mandelbaum and Shtub (2004) compared ways of running many projects and concluded that buffer management alone may not be enough: controlling how many projects are in progress at once matters at least as much.

Choosing a tool? Our guide CCPM Software in 2026: 13 Tools and How to Choose gives two simple tests for any CCPM tool and lists the options from A to Z.

Is CCPM right for you?

CCPM is a strong fit when

  • many projects compete for the same people, skills or equipment;
  • deadlines slip even though each task “looked fine”;
  • people switch between projects every day and priorities change weekly;
  • you need to promise dates you can keep, for customers or for launches.

CCPM adds less when

  • you run one project at a time with a dedicated team;
  • the work is mostly repetitive operations, not projects;
  • leadership isn’t ready to stop judging people on individual task dates;
  • the real problem is a lasting shortage of one skill. CCPM will show it clearly, but only more capacity or less work fixes it.

Not sure? Read CCPM vs. Critical Path: when to use each.

CCPM examples by industry

If the checklist above sounds familiar, you are in good company. CCPM turns up wherever many projects share scarce skills, from labs to hangars:

3×
Endress+Hauser

3× throughput with the same resources, as far as measurable.

≈ 50%
SICK

Approximately 50% fewer project delays in its development environment.

2×+
MEIKO

More than doubled completed projects after implementing LYNX and CCPM in 2021.

Results reported by each customer after introducing CCPM with LYNX. Each comes from a different context, and results depend on the starting point.

Running CCPM with LYNX

Everything above works on paper for one project. Across a portfolio, the levelling, buffer recalculation and priorities have to be kept up to date every day, which is why most organisations use software. LYNX by A-dato detects the critical chain for you, supports project, feeding and milestone buffers, shows portfolio status in a fever chart or heat map, and gives every role synchronised operational priorities. Teams that work with Kanban boards keep them, with the same priorities applied (LYNX Flow).

Theory is one thing. Here is what the CCPM steps from this guide look like on screen, for three different roles:

LYNX: one method, three views
LYNX progress chart (fever chart): projects plotted by critical chain completed against project buffer consumed, with rising red, orange and green zones

Progress chart (fever chart). Every project on one chart. Management sees at a glance which projects are in the red zone and need help, and leaves the green ones alone. CCPM step 7: manage the buffers.

LYNX project list in LYNX-X: released projects sorted by priority, each with critical chain progress, project buffer use and a red, orange or green status

Project list. Every released project, sorted by priority. For each one: how much of the critical chain is done, how much of the project buffer is used, and its status in red, orange or green. In the CCPM column, clc/cc 43d/53d means the current longest chain still needs 43 days, against a critical chain of 53 days, and pbp/pb 9d/27d means 9 of the 27 project buffer days are used. CCPM steps 4 and 5: critical chain and buffers, calculated for you.

LYNX TameFlow board in LYNX-X: cards in Open, Analysis, Development (buffer), Development, Review and Done columns, one lane per project workpackage with its priority, each card with its buffer use in red, orange or green

LYNX TameFlow board. Teams keep working on a board, one lane per workpackage. Each lane shows the project’s priority, and each card shows how much of its buffer is used in red, orange or green, so everyone can see what to pick up next without waiting for a meeting. CCPM step 7, for the people doing the work.

LYNX interface illustrations with sample data. Select an image to enlarge it.
Release work deliberatelyScenario and release planning show when a new project fits the capacity of your most heavily loaded skills.
Level resources by skillPlans use people’s skills and availability, so the critical chain is resource-feasible from the start.
Fits your systemsConnects to Jira and Azure DevOps, and imports from and exports to MS Project (XML files).
Start smallBegin with one team or one portfolio, then add capabilities as people get used to the method.

CCPM terms at a glance

Critical chain
The longest chain of dependent work once both task order and resource availability are taken into account.
Focused estimate
A task duration without individual safety time: aggressive but achievable, roughly a 50% chance of being met.
Project buffer
Shared safety time at the end of the critical chain that protects the delivery date.
Feeding buffer
Safety time where a side chain joins the critical chain.
Buffer penetration
Another name for buffer consumption, used in many CCPM tools.
Buffer consumption
The share of a buffer used so far. Read together with how much of the chain is complete, it gives the buffer status.
Fever chart
A chart of buffer consumed against chain completed, with red, orange and green zones.
Remaining duration
How many days a task still needs. CCPM asks for this instead of “% complete”.
Relay-runner ethic
Start chain work as soon as it arrives, finish it without switching, hand it over at once.
Staggering (pipelining)
Releasing new projects according to the capacity of the most heavily loaded skill.
Drum
In multi-project CCPM, the most heavily loaded (strategic) skill or resource. Its schedule sets the pace at which new projects are released.

Frequently asked questions

What does CCPM stand for?

CCPM stands for Critical Chain Project Management. It is a project planning and execution method based on Eliyahu Goldratt’s Theory of Constraints.

What is the critical chain in project management?

The critical chain is the longest sequence of dependent work in a project when both task dependencies and resource availability are taken into account. It determines how long the project takes; the project buffer at its end protects the promised date.

What is the difference between critical chain and critical path?

The critical path considers only task dependencies and assumes resources are available. The critical chain also considers resource dependencies, removes padding from individual tasks and protects the end date with buffers.

Who developed CCPM?

Dr. Eliyahu M. Goldratt, founder of the Theory of Constraints. He first presented the idea in 1990 and described it in his 1997 book Critical Chain.

What are the buffers in CCPM?

Classic CCPM has three: the project buffer at the end of the critical chain, feeding buffers where non-critical chains join the critical chain, and resource buffers, which are alerts rather than time, so critical resources are ready on time. Many tools add milestone buffers for intermediate deadlines, and multi-project CCPM adds a capacity buffer in front of the drum resource.

How big should a CCPM project buffer be?

The classic rule of thumb is 50% of the safety time removed from tasks on the critical chain. Other sizing methods exist, such as Newbold’s square-root-of-the-sum-of-squares method, and the right size depends on the type of project and how much uncertainty it carries. For long chains, the 50% rule can produce a larger buffer than needed.

What is buffer penetration in CCPM?

Buffer penetration (or buffer consumption) is the share of a buffer that delays have used up so far. It is always read together with how much of the chain is complete: 40% of the buffer used with 80% of the chain done is fine; with 20% done it is a red flag.

What is a fever chart in CCPM?

A fever chart plots buffer consumption against critical-chain completion. Red, orange and green zones show whether a project needs action now, needs a recovery plan, or is on track.

How does CCPM work across multiple projects?

Each project keeps its own critical chain and buffers. New projects are released only when the most heavily loaded skills have capacity, and buffer status sets priorities across all projects with one rule. Research suggests limiting the number of projects in progress matters as much as buffer management.

Is CCPM suitable for Agile or hybrid environments?

It can be. CCPM is often used to govern priorities and flow across a portfolio while teams execute work with Agile or Kanban practices. Software that supports both makes this combination practical.

What are the disadvantages of CCPM?

Researchers question fixed rules of thumb such as the 50% buffer and note that the critical chain can change as work progresses. In practice, the hardest part is behaviour: focused estimates only work when people aren’t blamed for individual task overruns.

Do I need software to use CCPM?

Not for a single simple project. For multiple projects sharing resources, software is practically necessary, because resource levelling, buffer recalculation and priority updates must happen continuously.

See what CCPM looks like across your projects.

LYNX brings critical chain scheduling, buffer management and portfolio priorities into one system.

Book a demo

Keep reading

References

  1. Altarazi, F., & Bao, H. (2015). Investigating the impact of buffer size in critical chain management. FAIM2015, 1–8.
  2. Cohen, I., Mandelbaum, A., & Shtub, A. (2004). Multi-project scheduling and control: A process-based comparative study of the critical chain methodology and some alternatives. Project Management Journal, 35(2), 39–50.
  3. Ghaffari, M., & Emsley, M. (2015). Current status and future potential of the research on Critical Chain Project Management. Surveys in Operations Research and Management Science, 20(2), 43–54. https://doi.org/10.1016/j.sorms.2015.10.001
  4. Goldratt, E. M. (1997). Critical Chain. Great Barrington, MA: The North River Press.
  5. Herroelen, W., & Leus, R. (2001). On the merits and pitfalls of critical chain scheduling. Journal of Operations Management, 19(5), 559–577.
  6. Hu, X., Demeulemeester, E., Cui, N., Wang, J., & Tian, W. (2016). Improved critical chain buffer management framework considering resource costs and schedule stability. Flexible Services and Manufacturing Journal, 29(2), 159–183. https://doi.org/10.1007/s10696-016-9241-y
  7. Kendall, G. (2020). Critical chain and critical path – what’s the difference?
  8. Leach, L. P. (1999). Critical chain project management improves project performance. Project Management Journal, 30(2), 39–51. https://doi.org/10.1177/875697289903000207
  9. Newbold, R. C. (1998). Project Management in the Fast Lane: Applying the Theory of Constraints. St. Lucie Press.
  10. Parkinson, C. N. (1955, November 19). Parkinson’s Law. The Economist.
  11. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) (6th ed.). Project Management Institute.
  12. Rubinstein, J. S., Meyer, D. E., & Evans, J. E. (2001). Executive control of cognitive processes in task switching. Journal of Experimental Psychology: Human Perception and Performance, 27(4), 763–797.
  13. Weinberg, G. M. (1992). Quality Software Management, Vol. 1: Systems Thinking. Dorset House.

A-dato makes LYNX, software for running CCPM across a portfolio of projects. This article explains the method in general; product details are limited to the LYNX section.

Previous Post
#LYNXTips: Boost Team Collaboration & Efficiency with LYNX!
Next Post
Harnessing ISA95 for Resource Management in LYNX

Put your Project Portfolio into Motion with LYNX.

No results found.

Leave a Reply

Your email address will not be published. Required fields are marked *

Fill out this field
Fill out this field
Please enter a valid email address.